|
Module 18: Managing PPPs
18.4. Renegotiation
The public-private partnership process does not end when the private
partner is chosen and all the relevant papers are signed. It is not possible
for a contract to handle all the uncertainties that the future holds.
Thus, careful provision must be made to deal with unexpected events over
the life of the contract.
For short-term contracts, renegotiation would seem to be
unnecessary provided adequate and automatic safeguard procedures for
changes in conditions have been built into the contract. However, in
the real world governments change and the new people in power may be
dissatisfied with the initial contract terms. Thus, it is prudent to
specify renegotiation procedures clearly and to allow independent arbitration
if necessary.
In addition, the contract could require amendments if the
legitimate needs of the users of the service are not satisfied within
the agreed boundaries of the contract.
Even more critical, however, is the presence of a renegotiation
statement in the medium- and long-term contracts that constitute the
majority of PPP projects. The poorer the quality of information from
the start, and the greater the doubts of both parties about their relationship,
the better will be the chance that renegotiations will have to occur.
Therefore, it is important to introduce clear provisions for renegotiation
and to supplement competition at the bidding stage with future competitive
pressures.
However, before there is a need for a contract renegotiation,
it would be wise to try resolving some of the problems within the present
contract terms and conditions. If this does not appear feasible/possible,
a PPP Review Panel could be established. This is an independent body
that all parties would respect, which could be consulted to resolve issues.
The panel would be consulted before resorting to arbitration or other
legal measures that could take years to decide, during which time the
PPP would almost certainly fail [see Tool 19].
Elements of the contract on renegotiation
The service provider and the municipality should have the
right to renegotiate and the ability to do so if special
circumstances arise, such as if revenues are substantially off target
(either too low to cover costs, or too high and generating too much
profit), or if a structural problem (such as a problem with the underground
water supply) is discovered by the provider, which was not considered
in the original bid. In such cases, both the public and private parties
should follow the mechanisms to request renegotiation and
to renegotiate and settle the issue as described in the contract.
Renegotiation should be covered as part of the contractual
arrangements, with clear statements about the following:
• The conditions under which adjustment of terms or renegotiation
may occur.
• Who can request renegotiation of the contract?
• How often can renegotiation occur?
• What extensions to the contract – such as adding treatment
works or a new service district – allow or require re-tendering the
contract?
• What is the process by which renegotiation must be initiated and
conducted?
• What are the procedures to be followed, and the organisations or
individuals to be appealed to in the event that the parties to the contract
cannot agree on how to resolve an issue (arbitration provisions).
In most cases where problems have arisen in PPP arrangements
in the past, contractual difficulties have been worked out
through adjustment or renegotiation of key contract terms. Such renegotiation
requires good faith on the part of both the government and the private
operator. Where a good working relationship and collaborative spirit are
lacking, on the other hand, or where political motivations prevent governments
from negotiating, contract termination is the result of such problems.
Termination of the contract is not beneficial to either of
the parties, unless the new, renegotiated terms were entirely
unacceptable. First and foremost, termination means that the process
has to start again from the very beginning; the additional effort required
to build new relationships and conduct new negotiations also brings with
it additional transaction costs. Thus provision for renegotiation is
vital for the implementation of a successful PPP. In order to prevent
and mitigate conflicts and subsequent contract termination, conflict
resolution skills should be included in the capacity development trainings
[Tools 20, 21].
End of Module 18

© 2004 UNDP, Manufactured
by Margraf Publishers GmbH, Germany |