Main UNDP Home Page    
UNDP Homepage UNDP Homepage UNDP Homepage
UNDP logodividerdividerdividerdivider
15.1 What is the process of regulation?
15.2 Alternative regulatory arrangements
15.3 What is the scope of regulation?
15.4 Background to the process of creating a new regulatory body
15.5 Some regulatory pitfalls
15.6 Regulation in low-income environments

 

 

 

 

Module 15: Regulating the PPP


15.5. Some regulatory pitfalls

 

There follow some examples of possible regulatory pitfalls where the relationship between the basic services provider and the contract supervisor (or regulator) has become too comfortable, where it is poor or where it has broken down altogether.


1. By-passing the regulator

On a concession in Latin America, the private concessionaire bypassed the regulator on a number of key issues in order to deal with government directly. The credibility of the regulator was undermined, bringing into question the effectiveness of the regulatory mechanisms that were in place.


2. Distrust of foreign private management

A management contract in the Caribbean was frustrated due to antagonism amongst members of the supervising board to the presence of a foreign private manager. The board was obstructive, and this impaired the ability of the manager to perform. The situation led to the ultimate early termination of the contract.


3. Lack of finance

There was a case when a PPP arrangement, which depended heavily on the donor money, failed because the promised donor funding did not materialise due to macro-economic circumstances. This meant that the operator was unable to implement the investment programme and hence deliver the performance improvements it had agreed with the regulator.


4. Failure of the state to fulfil its obligations

The operator appointed for a PPP contract in Africa was unable to deliver the agreed performance improvements because the state-owned asset holding company failed to deliver its contractual commitment to fund the renewal of major plant. This resulted in financial stress on the operator.


5. Ineffective relationship between regulator and government or utility (regulatory capture)

Where a regulator’s sphere of activity is confined to a single supplier, or where external pressure and accountability are absent, a regulator can become over-familiar with the interests of one party or another in the partnership arrangement. With the commercial advantage weighed towards the operator, the regulator can, by stealth, become dependent upon the operator for information; this in turn may result in a perceived “cosy relationship” between the regulator and the regulated. Such a situation can arise, for instance, where there is a split between the organisation responsible for providing bulk water (under government ownership) and that responsible for distribution to consumers (under PPP). An example of such an arrangement existed in southern Africa, where the private distribution operator depended upon bulk supplies from several state-owned water boards. Although these boards were in effect governmental, in reality they operated autonomously with little regulatory pressure and as effective monopolies with a free hand in setting tariffs and standards. This undermined the performance of the PPP operator. Similarly, in Eastern Europe municipality-based regulators have been criticised in audits for procedural failings.


6. Micro management

There are examples where the regulatory/supervisory body has become too closely involved in the day-to-day management of the utility, rather than focusing on key strategic issues such as service provision to low-income groups. This can introduce considerable additional bureaucracy for the operator and hampers both the operator’s progress and regulatory processes. Furthermore, by blurring the role of “provider” and “client”, the regulator may reduce its own ability to enforce the contract.


7. Political interference

There is an inherent danger that political imperatives – for instance, price pressures – will conflict with the principles of good regulation. In one example, political pressure was placed on a concessionaire to serve areas that were not financially viable, without first allowing tariff adjustments and cross-subsidisation from other customers to take place. In the UK, political imperatives have prevailed on several occasions by imposing one-off windfall taxes on profits, or by encouraging the regulator to zealously pursue price reduction against the longer-term interests of sustainability in the water sector.

A pragmatic balance has to be struck between the various pressures. In the early days of a PPP regime, the regulator invariably focuses on the following key issues:

◊ establishing a professional working relationship with the private operator and a mutual understanding of the sector issues, whilst at the same time striking a balance between antagonism and an over-comfortable relationship;

◊ adhering to the legal and contractual powers and responsibilities described in the law, licence or contract, but focusing at all times on key issues that affect customers or potential future customers;

◊ establishing numerical bases for determining whether levels of service are improving or getting worse; and

◊ periodically reviewing and updating the operator’s plan to ensure that it is continually relevant – especially in relation to connections, expansion and provision of new services (including those to low-income customers).

© 2004 UNDP,  Manufactured by Margraf Publishers GmbH, Germany

Access to the Modules:
divider
S T A R T P A G E
divider
01-Starting out
divider
02-Strategic Planning
divider
 03-Planning & Organising
divider
 04-Collecting Information
divider
05-Identifying Constraints
divider
06-Defining Objectives
divider
07-Defing Parameters (Scope)
divider
08-Establishing Principles
divider
09-Identifying Partners
divider
10-Establishing Partnership
divider
11-Selecting Options
divider
12-Financing (Investment)
divider
13-Financing (Cost Recovery)
divider
14-Preparing Business Plans
divider
 – 15-Regulating the PPP –
divider
16-Tendering & Procurement
divider
17-Negotiating & Contracting
divider
18-Managing PPPs
divider
19-Monitoring & Evaluation
divider
20-Managing Conflict
divider
21-Building Development
divider