|
Module 15: Regulating the PPP
15.5. Some regulatory pitfalls
There follow some examples of possible regulatory pitfalls where the
relationship between the basic services provider and the contract supervisor
(or regulator) has become too comfortable, where it is poor or where
it has broken down altogether.
1. By-passing the regulator
On a concession in Latin America, the private
concessionaire bypassed the regulator on a number of key
issues in order to deal with government directly. The credibility of
the regulator was undermined, bringing into question the effectiveness
of the regulatory mechanisms that were in place.
2. Distrust of foreign private management
A management contract
in the Caribbean was frustrated due to antagonism amongst
members of the supervising board to the presence of a foreign
private manager. The board was obstructive, and this impaired
the ability of the manager to perform. The situation led
to the ultimate early termination of the contract.
3. Lack of finance 
There was a case when a PPP arrangement,
which depended heavily on the donor money, failed because
the promised donor funding did not materialise due to macro-economic
circumstances. This meant that the operator was unable to
implement the investment programme and hence deliver the
performance improvements it had agreed with the regulator.
4. Failure of the state to fulfil its obligations 
The
operator appointed for a PPP contract in Africa was unable
to deliver the agreed performance improvements because
the state-owned asset holding company failed to deliver
its contractual commitment to fund the renewal of major
plant. This resulted in financial stress on the operator.
5. Ineffective relationship between regulator and government
or utility (regulatory capture) 
Where a regulator’s sphere of
activity is confined to a single supplier, or where external
pressure and accountability are absent, a regulator can become over-familiar
with the interests of one party or another in the partnership arrangement.
With the commercial advantage weighed towards the operator,
the regulator can, by stealth, become dependent upon the operator for
information; this in turn may result in a perceived “cosy relationship” between
the regulator and the regulated. Such a situation can arise,
for instance, where there is a split between the organisation responsible
for providing bulk water (under government ownership) and that responsible
for distribution to consumers (under PPP). An example of such an arrangement
existed in southern Africa, where the private distribution operator depended
upon bulk supplies from several state-owned water boards. Although these
boards were in effect governmental, in reality they operated autonomously
with little regulatory pressure and as effective monopolies with a free
hand in setting tariffs and standards. This undermined the performance
of the PPP operator. Similarly, in Eastern Europe municipality-based
regulators have been criticised in audits for procedural failings.
6. Micro management 
There are examples where the regulatory/supervisory
body has become too closely involved in the day-to-day management
of the utility, rather than focusing on key strategic issues
such as service provision to low-income groups. This can
introduce considerable additional bureaucracy for the operator
and hampers both the operator’s progress
and regulatory processes. Furthermore, by blurring the role
of “provider” and “client”,
the regulator may reduce its own ability to enforce the contract.
7. Political interference 
There is an inherent danger that
political imperatives – for instance, price pressures – will
conflict with the principles of good regulation. In one example, political
pressure was placed on a concessionaire to serve areas that were not
financially viable, without first allowing tariff adjustments and cross-subsidisation
from other customers to take place. In the UK, political imperatives
have prevailed on several occasions by imposing one-off windfall taxes
on profits, or by encouraging the regulator to zealously pursue price
reduction against the longer-term interests of sustainability in the
water sector.
A pragmatic balance has to be struck between the various
pressures. In the early days of a PPP regime, the regulator
invariably focuses on the following key issues:
◊ establishing a professional working relationship with the private operator
and a mutual understanding of the sector issues, whilst at the same time striking
a balance between antagonism and an over-comfortable relationship;
◊ adhering to the legal and contractual powers and responsibilities described
in the law, licence or contract, but focusing at all times on key issues that
affect customers or potential future customers;
◊ establishing numerical bases for determining whether levels of service
are improving or getting worse; and
◊ periodically reviewing and updating the operator’s plan to ensure
that it is continually relevant – especially in relation to connections,
expansion and provision of new services (including those to low-income customers).

© 2004 UNDP, Manufactured
by Margraf Publishers GmbH, Germany |